Construction Progress

September 21, 2024 – Asphalt completed

Asphalt Completed
Asphalt Completed
Asphalt Completed

September 21, 2024 – First hangar is getting ready for paint

Hangar Getting Ready for Paint

September 12, 2024 – Ready for asphalt

Ready for Asphalt

September 12, 2024 – Rough electrical and plumbing completed, sheet rock in process

Hangar Interior
Hangar Interior

August 26, 2024 – Center taxiway drain installed, preparing for paving

Center taxiway drain

August 19, 2024 – Signage on end of buildings going up

Hangar Signage Going Up
Hangar 1 Signage Completed
Hangar 4 Signage Completed
Hangar 9 Signage Completed

July 22, 2024 – Brick work nearing completion on North Hangar

North Hangars East Side Brick Work Almost Complete
North Hangar West Side Brick Work Complete

July 11, 2024 – Both hangars brick work completed on West side

Western Fab Hangars Brick Work Complete

July 8, 2024 – South Hangars East and West sides brick work progressing, and overhead lighting progressing

South Hangars East Side Brick Work Progressing
South Hangars West Side Brick Work Progressing
South Hangars Overhead Lighting Progressing

July 8, 2024 – North Hangars West side brick work completed, hangar doors almost complete

North Hangars West Side Brick Work Completed
North Hangars Doors Almost Complete

June 25, 2024 – Both hangars interior electrical started, South hangars drywall has arrived, North hangars interior framing in process and brick work started

Both Hangars Electrical Started
South Hangars Drywall Arrived
North Hangars Interior Framing in Process
North Hangars Brick Work Started

June 18, 2024 – South Hangars heated cement apron poured, HVAC installation started, and hangar doors sided and insulated. Both hangars ready for brick work.

South Hangars Heated Cement Apron Poured
South Hangars HVAC Installation Started
South Hangars Doors Sided and Insulated
Both Hangars Ready for Brick Work

May 23, 2024 – North Hangars concrete complete

North Hangar Concrete Complete
North Hangar Concrete Complete

May 23, 2024 – South Hangars doors nearing completion

South Hangar Doors Nearing Completion

May 2, 2024 – South Hangars (#1) office mezzanine framing started

Hangar 1 Office Mezzanine Framing

May 2, 2024 – North Hangars 6-8 ready for concrete

North Hangar Ready for Concrete

May 2, 2024 – South Hangars doors framed in

South Hangar Doors Framed
South Hangar Doors Framed

April 17, 2024 – North Hangars – plywood up, ready for windows then brick. Plumbing complete, almost ready for concrete.

North Hangar Plywood Up
North Hangar Plumbing Complete Ready for Concrete

April 11, 2024 – South Hangars Concrete Complete, Hangars 1-4

South Hangar Concrete Complete

April 3, 2024 – North Hangars – Ceiling insulation almost complete, West wall framing started prior to brick work

North Hangar Ceiling Insulation

April 3, 2024 – South Hangars – Concrete almost complete, 1 more day of pouring to go

South Hangar Concrete

April 3, 2024 – East View of Hangars, Plywood up ready for brick. Sample of bricks.

East View Hangars
Sample of Bricks

March 25, 2024 – North hangars siding installation

North Hangar Siding
North Hangar Siding

March 25, 2024 – South hangars concrete progress

South Hangar Concrete
South Hangar Concrete

March 18, 2024 – South hangars ready for concrete

South Hangar Ready for Concrete

March 6, 2024 – Steel framing progressing on both hangars

Framing on Both Hangars

March 6, 2024 – South hangars plumbing started

South Hangar Plumbing Started

February 21, 2024, North hangars steel framing started

North Hangar Steel Framing
North Hangar Steel Framing

January 31, 2024, North hangars finishing back fill and inside foundation walls

North Hangar Inside Foundation

January 31, 2024, South hangars framing started

South Hangar Steel Framing

January 16, 2024, South hangars floors leveled, staging steel

South Hangar Floor Leveled

January 16, 2024 – North hangars foundation walls completed

North Hangar Foundation Walls

December 29, 2023, North hangars footings preparation

North Hangar Footing Formed

December 29, 2023, South hangars foundation

South Hangar Foundation

December 2023, South hangars foundation being formed

South Bldg Foundation Formed

December 2023, South hangars footings formed

South Bldg Footing Formed
South Bldg Footing Formed

November 2023, getting ready for footings

North Building Footings
South Building Footings

November 2023, steel shipment has arrived

Steel Shipment Arrival
Steel Shipment Arrival
Steel Shipment Arrival

September 27, 2023 – Asphalt getting laid down

Western Fab Hangars Construction Progress

September 22, 2023 – Curb and gutter installed

Western Fab Hangars Construction Progress

September 13, 2023 – Old building has been demolished. Redwood Road is being widened, and underground utilities are being installed.

Western Fab Hangars Construction Progress

May 2023, old building that will be demolished

Original building on site