Construction Progress
September 21, 2024 – Asphalt completed
September 21, 2024 – First hangar is getting ready for paint
September 12, 2024 – Ready for asphalt
September 12, 2024 – Rough electrical and plumbing completed, sheet rock in process
August 26, 2024 – Center taxiway drain installed, preparing for paving
August 19, 2024 – Signage on end of buildings going up
July 22, 2024 – Brick work nearing completion on North Hangar
July 11, 2024 – Both hangars brick work completed on West side
July 8, 2024 – South Hangars East and West sides brick work progressing, and overhead lighting progressing
July 8, 2024 – North Hangars West side brick work completed, hangar doors almost complete
June 25, 2024 – Both hangars interior electrical started, South hangars drywall has arrived, North hangars interior framing in process and brick work started
June 18, 2024 – South Hangars heated cement apron poured, HVAC installation started, and hangar doors sided and insulated. Both hangars ready for brick work.
May 23, 2024 – North Hangars concrete complete
May 23, 2024 – South Hangars doors nearing completion
May 2, 2024 – South Hangars (#1) office mezzanine framing started
May 2, 2024 – North Hangars 6-8 ready for concrete
May 2, 2024 – South Hangars doors framed in
April 17, 2024 – North Hangars – plywood up, ready for windows then brick. Plumbing complete, almost ready for concrete.
April 11, 2024 – South Hangars Concrete Complete, Hangars 1-4
April 3, 2024 – North Hangars – Ceiling insulation almost complete, West wall framing started prior to brick work
April 3, 2024 – South Hangars – Concrete almost complete, 1 more day of pouring to go
April 3, 2024 – East View of Hangars, Plywood up ready for brick. Sample of bricks.
March 25, 2024 – North hangars siding installation
March 25, 2024 – South hangars concrete progress
March 18, 2024 – South hangars ready for concrete
March 6, 2024 – Steel framing progressing on both hangars
March 6, 2024 – South hangars plumbing started
February 21, 2024, North hangars steel framing started
January 31, 2024, North hangars finishing back fill and inside foundation walls
January 31, 2024, South hangars framing started
January 16, 2024, South hangars floors leveled, staging steel
January 16, 2024 – North hangars foundation walls completed
December 29, 2023, North hangars footings preparation
December 29, 2023, South hangars foundation
December 2023, South hangars foundation being formed
December 2023, South hangars footings formed
November 2023, getting ready for footings
November 2023, steel shipment has arrived
September 27, 2023 – Asphalt getting laid down
September 22, 2023 – Curb and gutter installed
September 13, 2023 – Old building has been demolished. Redwood Road is being widened, and underground utilities are being installed.
May 2023, old building that will be demolished