Construction Progress
September 21, 2024 – Asphalt completed



September 21, 2024 – First hangar is getting ready for paint

September 12, 2024 – Ready for asphalt

September 12, 2024 – Rough electrical and plumbing completed, sheet rock in process


August 26, 2024 – Center taxiway drain installed, preparing for paving

August 19, 2024 – Signage on end of buildings going up




July 22, 2024 – Brick work nearing completion on North Hangar


July 11, 2024 – Both hangars brick work completed on West side

July 8, 2024 – South Hangars East and West sides brick work progressing, and overhead lighting progressing



July 8, 2024 – North Hangars West side brick work completed, hangar doors almost complete


June 25, 2024 – Both hangars interior electrical started, South hangars drywall has arrived, North hangars interior framing in process and brick work started




June 18, 2024 – South Hangars heated cement apron poured, HVAC installation started, and hangar doors sided and insulated. Both hangars ready for brick work.




May 23, 2024 – North Hangars concrete complete


May 23, 2024 – South Hangars doors nearing completion

May 2, 2024 – South Hangars (#1) office mezzanine framing started

May 2, 2024 – North Hangars 6-8 ready for concrete

May 2, 2024 – South Hangars doors framed in


April 17, 2024 – North Hangars – plywood up, ready for windows then brick. Plumbing complete, almost ready for concrete.


April 11, 2024 – South Hangars Concrete Complete, Hangars 1-4

April 3, 2024 – North Hangars – Ceiling insulation almost complete, West wall framing started prior to brick work


April 3, 2024 – South Hangars – Concrete almost complete, 1 more day of pouring to go

April 3, 2024 – East View of Hangars, Plywood up ready for brick. Sample of bricks.


March 25, 2024 – North hangars siding installation


March 25, 2024 – South hangars concrete progress


March 18, 2024 – South hangars ready for concrete

March 6, 2024 – Steel framing progressing on both hangars

March 6, 2024 – South hangars plumbing started

February 21, 2024, North hangars steel framing started


January 31, 2024, North hangars finishing back fill and inside foundation walls

January 31, 2024, South hangars framing started

January 16, 2024, South hangars floors leveled, staging steel

January 16, 2024 – North hangars foundation walls completed

December 29, 2023, North hangars footings preparation

December 29, 2023, South hangars foundation

December 2023, South hangars foundation being formed

December 2023, South hangars footings formed


November 2023, getting ready for footings


November 2023, steel shipment has arrived



September 27, 2023 – Asphalt getting laid down

September 22, 2023 – Curb and gutter installed

September 13, 2023 – Old building has been demolished. Redwood Road is being widened, and underground utilities are being installed.

May 2023, old building that will be demolished